A turnaround packs weeks of contractor labor, equipment, and change orders into a few weeks of billing. When the turnaround window compresses, the billing compresses with it. Thousands of field tickets come in while a lean team is focused on schedule, safety, and scope. When costs drift, it's rarely one bad decision. It's a series of small gaps that repeat across hundreds of invoices.

Where the findings come from

Here is how findings from Revenew's turnaround invoice reviews break down by category:

  • Per diem: 23%
  • Tools and consumables: 22%
  • Equipment rates: 16%
  • Payroll reporting: 13%
  • Overheads: 7%
  • Exempt pay issues: 6%
  • Taxes: 2%
  • Other: 11%

Most of it is routine billing that was never checked against the contract, not wrongdoing.

Four places it drifts

Per diem

Eligibility depends on distance, residence, and days actually worked. On a large crew, per diem can be billed for days with no hours, for workers whose primary residence is local, or twice for the same day.

Tools, consumables, and equipment

Small tools and consumables add up fast at turnaround volume. Equipment rates may not match the contract, standby gets billed outside the agreed terms, and rentals can keep billing after the equipment leaves the site.

Rates in the system

If a contract's pricing terms never fully make it into the system, manual entries fill the gap. From then on, every invoice is checked against the wrong number.

Change orders

Some cover work already in the base scope. Others sit unpriced until the work is done, when the pricing conversation is harder to have.

Why it still looks right

Each ticket is approved against what's in the system. If the system rate is wrong, the invoice matches it perfectly. During a major event, nobody has time to recheck rates line by line.

What to check before mobilization

  • Rate schedules in your system match the signed contracts for your largest contractors
  • Per diem eligibility rules are written down and shared with each contractor
  • Change order pricing and approval authority are agreed before work starts
  • Billing review closes at demobilization, so nothing unverified carries past restart

Keeping it collaborative

None of this needs to strain contractor relationships. When issues are handled as rate and contract questions, documented at the invoice level and settled directly with the contractor, they get resolved faster, and the next contract is clearer for both sides.

If you're planning a 2027 turnaround and want your largest contractors' rates checked before mobilization, see how our pre-mobilization check works.